← All templates⤓ Edit in Excel (.xlsx)
VAVEhub · Toolkit 11

Target-Cost Cascade

Start from what the market will pay and work down: the allowable cost for the product, then each system, then each part.

Step 1 · The allowable cost

Shop or list price
− VAT
− Dealer or retailer margin
Net selling price (what the business actually receives)
Required margin (% and £)
Allowable cost = net selling price − margin

Step 2 · Split the allowable cost across systems

SystemShare %Why this share (function worth, benchmark)Target £Current cost £Value gap £Gap % of currentOwner (named engineer)
Total and reserve

Keep a small reserve that isn't given to anyone, because designs change. Every target has a named engineer as owner, not a department.

Step 3 · Split one system into parts

Part or subsystemShare %Why this shareTarget £Current cost £Value gap £Gap % of currentOwner
Total

Step 4 · Close the gap

ChangeLever (design, material, process, sourcing…)Saving £StatusOwner
Total saving · gap remaining
The one rule: the target cost is never exceeded. If a feature has to be added, its cost is saved somewhere else.
Worked example (Module 13): an EV with a net selling price of £29,900 and a 22% margin has an allowable cost of £23,322. The drive unit gets 9.8% (£2,286), and the motor 46% of that: a target of £1,052. The motor currently costs £1,214, a value gap of £162 (13%). Hairpin winding −£38, one housing casting instead of three −£61, magnet grade −£43, supplier gain-share on machining −£26: −£168 in total, with £6 going back to the reserve.
© Avinash Bhosale · VAVEhub Toolkit — free for personal & internal company use with attribution; commercial redistribution or resale prohibitedDesigned & Developed by Avinash Bhosale